4 bedroom maisonette - 42310

Build cost  KSh 14,072,481

4 Bedroom
3 Bathroom
30x60 and above

4 bedroom maisonette - 42310

Floor Plans

MaterialsLabour
ExcavationsKSh 0KSh 73,600
Foundations and hardcore fillingKSh 585,922KSh 117,600
Ground floor slabKSh 221,923KSh 128,800
Elecrical works(see separate document)KSh 20,000KSh 19,000
Plumbing and drainage(see separate document)KSh 94,590KSh 19,000
Ground floor WallingKSh 204,631KSh 123,200
Elecrical works(see separate document)KSh 30,000KSh 19,000
Plumbing and drainage(see separate document)KSh 70,000KSh 19,000
Ground and first floor columnsKSh 124,280KSh 41,600
Suspended first floor beams, slabs and staircaseKSh 993,793KSh 46,800
Elecrical works(see separate document)KSh 35,000KSh 21,000
Plumbing and drainage(see separate document)KSh 15,000KSh 11,400
First floor WallingKSh 246,769KSh 123,200
Elecrical works(see separate document)KSh 30,000KSh 19,000
Plumbing and drainage(see separate document)KSh 70,000KSh 19,000
Suspended Second floor beams, slabs and staircaseKSh 929,877KSh 46,800
Elecrical works(see separate document)KSh 35,000KSh 21,000
Plumbing and drainage(see separate document)KSh 15,000KSh 11,400
Second floor WallingKSh 130,938KSh 11,200
Elecrical works(see separate document)KSh 5,000KSh 2,200
Plumbing and drainage(see separate document)KSh 5,000KSh 2,200
Roof slab and beamsKSh 227,761KSh 30,800
Elecrical works(see separate document)KSh 5,000KSh 2,200
RoofingKSh 0KSh 0
ScreedsKSh 167,271KSh 0
WaterprooingKSh 265,384KSh 0
Protective tilesKSh 200,200KSh 0
Rain water pipes and guttersKSh 31,600KSh 67,200
Plumbing and drainage(see separate document)KSh 117,080KSh 21,400
PergolaKSh 121,662KSh 25,200
RailingKSh 139,500KSh 8,800
Plasterwork, floor screeds and window cillsKSh 352,754KSh 58,800
Windows (Steel casemnt windows)KSh 997,495KSh 48,400
DoorsKSh 535,545KSh 61,600
TilingKSh 955,037KSh 43,200
Plumbing and drainage(see separate document)KSh 39,310KSh 21,400
Kitchen, wardrobes, store shelving and mirrorsKSh 839,400KSh 0
Concrete plinth:KSh 13,034KSh 0
Concrete tops:KSh 2,719KSh 89,600
Wiring, sockets, switched and bulb holdersKSh 0KSh 0
Elecrical works(see separate document)KSh 100,000KSh 23,000
Toilets, showers, water tanks and sinksKSh 595,250KSh 21,400
PaintworkKSh 609,714KSh 39,200
Elecrical works(see separate document)KSh 5,000KSh 3,000
Waste water disposalKSh 285,000KSh 61,600
Ancillary structuresKSh 1,700,000KSh 150,000
Parking slotsKSh 0KSh 0
ExcavationsKSh 0KSh 22,400
MaterialsKSh 173,635KSh 35,200
When you buy this plan you'll get;
  • Architectural drawings in PDF format

  • Bills of materials and labour with budget costs

  • Access to a project management tool to help you manage your build

  • All engineering drawings

  • Access to Inuua verified suppliers and contractors